Practice question
After operations begin, monitoring is necessary to assess continuing environmental effects of the project. The State says the initial assessment permanently eliminates every monitoring issue. What did Pulp Mills paragraph 205 state?
- Where necessary, continuous monitoring is undertaken throughout the project’s life.
- All monitoring is forbidden
- A one-page initial form always ends due diligence
- Only foreign shareholders may monitor
- Monitoring must wait until all harm is irreversible
Legal references
- ICJ, Pulp Mills on the River Uruguay (Argentina v. Uruguay), Judgment, April 20, 2010, paragraphs 204-205: https://icj-web.leman.un-icc.cloud/sites/default/files/case-related/135/135-20100420-JUD-01-00-EN.pdf