Practice question
A covered project needs a parcel valued under an approved SMV. The land’s market value is P4 million, crops and trees are worth P200,000, and the applicable replacement cost of structures after consideration of depreciation is P1 million. The complaint is filed and due notice is given. For the initial Section 7(a) deposit, which total follows the ARROW Act percentages?
- P5,200,000
- P780,000
- P1,600,000
- P1,630,000
- P600,000
Legal references
- RA 10752, as amended by RA 12289 (September 12, 2025): https://elibrary.judiciary.gov.ph/thebookshelf/showdocs/2/99855; Section 7(a)(1)–(3).
Answer this question in flashcards to review your response and continue practicing.