A builder identifies a particular finishing phase and explains its scope and determinable duration when hiring workers. It later alleges completion but submits only a generic certificate concerning a different phase; the assigned finishing work is shown still ongoing. It says project classification automatically proves lawful termination. Which is correct?
  1. The label alone proves completion
  2. Any certificate from any site ends every worker’s contract
  3. The employer must establish completion of the undertaking for which these workers were engaged, or another lawful termination ground
  4. Project employees can never have a valid complaint
  5. Completion of a different phase always binds them

Legal references

  • Coogee, G.R. 264881, July 16, 2025: https://lawphil.net/judjuris/juri2025/jul2025/gr_264881_2025.html